top of page
AUG_Gallery_027.jpg

Construction Milestones.

Expected date of completion is mid-2027

August-October 2025

We continue to make headway on the Mountain Oak site, despite the mixed weather Queenstown has been experiencing. Stewart Civil has shaped up the North boundary and prepped the platform for some big cages.

Francis Ward, in partnership with Complete Reinforcing, set up and are plugging away at the foundation pads that are all over the place; and CLL Service and Solutions has completed 253 strands and 4320 metres of concrete piles. Plus, after lots of planning, permits, and correspondence, Smith Crane & Construction has put another tower crane up in the air. 

May-July 2025

We are well on our way to being in the swing of things with our various contractors. We have been working with Alliance Services, who has been entrusted to air vac the trenches and prep the site for the utility providers to do their thing.

At the same time, Stewart Civil has been undertaking civil construction work like excavations; and recently completed the first stage of earthworks. CLL Service and Solutions – a piling and foundation specialist – have started their testing methods.

Live on-site camera

TimescapesImage_Oct25.jpg
How to use Timescapes

01

Use the calendar / time and date icon to choose the exact time and date you want to view.

02

Select the image compare icon to choose two different days to view side by side.

03

Select the 3D model icon to see a model of the entire building on the site.

Market Street, Remarkables Park, Frankton

Render/images and videos are artist's impression only.

bottom of page